Closure work of girder between Pylon P12 and P13 was completed on 14th March, 2014.

Main bridge has 5 Pylons (P12, P13, P14, P15, P16) and Supesr strucrures on each pylons
are erected with cantilever erection, resulting 4 closre works totally.

3 closure works have been completed and final closure is scheduled on end of March/2014.